ENERGY SOURCES REQUIRE UPDATING

Reconstruction and modernization of equipment are in full swing at the enterprises of Almaty Electric Power Stations JSC

smi20.05.2014This was confirmed by journalists who visited CHPP-2, where the ash dump is being reconstructed, which is necessary for the stable operation of the enterprise. Prior to that, the plant had already repaired the fan cooling towers, which allowed to increase the volume of electricity production, and built a boiler room, thanks to which the heat output increased to 1 million tons. Gcal per year, reconstructed ash collection facilities and much more.
In general, according to Galym Zhanbyrshi, Deputy Chairman of the Board for Development of AlES JSC, all these works are carried out within the framework of fulfilling investment obligations, which in 2009-2013 amounted to 59.4 billion tenge.
“These funds were used to increase production volumes and reduce production costs,” Galym Zhanbyrshi said. – As well as to maintain the current level of production, construction of ash dumps and environmental protection measures. Reconstruction of fan cooling towers at CHPP-2 and CHPP-3 allowed to increase the volume of electricity production by 549.7 million kW per year. The construction of ash dumps at all three CHPPs is part of the continuous technological cycle of coal-fired power plants and is necessary for the uninterrupted supply of electric and thermal energy to consumers in Almaty and the Almaty region. Environmental protection measures, such as the reconstruction of ash collection plants and modernization of burner devices, have reduced inorganic dust emissions by more than 10 thousand tons per year.
In addition, according to the Deputy Chairman of the Management Board for Development, measures to reconstruct and replace equipment to maintain the current level of production have reduced the number of emergency shutdowns from 153 in 2009 to 100 in 2013.

Our Help

JSC AlES, which is part of the Samruk-Energo Group of Companies, is an energy-producing organization that provides about 72 percent of electric and 70 percent of thermal energy in Almaty and the Almaty region. The average weighted depreciation of the main equipment of AlES power sources is 60-70 percent. The equipment of CHPP-1, CHPP-3 and HPP Cascade has the greatest wear and tear.

Irina TULINOVA

INVESTMENTS IN RELIABILITY AND QUALITY (EXECUTION OF THE INVESTMENT AGREEMENT OF ALES JSC WITH THE MINISTRY OF INDUSTRY AND TRADE OF THE REPUBLIC OF KAZAKHSTAN FOR 2013)

According to the investment agreement concluded with the Ministry of Industry and New Technologies of the Republic of Kazakhstan, AlES JSC’s investment obligations for 2013 are planned to amount to KZT 7,580. 1 million, with actual fulfillment amounting to KZT 7,550.9 million (99.6%).
The following main activities were implemented under the Investment Agreement::
Measures aimed at increasing production volumes, including::
* Reconstruction and expansion of CHPP-1 of JSC “AlES” with conversion to gas and installation of CCGT/GTU. Development of POI. Completion of work in 2014
* Clearing of the riverbed in the lower reaches of the Kapshagai hydroelectric power station. Completion of work in 2014
• ” Reconstruction of HPP-2 of the HPP Cascade. Development of POI”. Completion of work in 2014
Measures to reduce production costs, including::
* Construction of its own water intake at CHPP-1 and CHPP-2. Completion of work in 2014
* Installation of water metering devices at Kapshagayskaya HPP. Completion of work in 2014
Maintaining the production level
To replace physically worn-out equipment and extend its service life, the power equipment of CHPP-1, CHPP-2, CHPP-3, Kapshagayskaya HPP and Cascade of HPPs was reconstructed in the amount of 2,598. 3 million tenge, including:
* Major repair of hydraulic unit no.2 Kapshagayskaya HPP with complete disassembly and instrumental surveys to determine the remaining resource.
* Reconstruction and construction of buildings and structures has been completed.
• The medium-speed roller mill was replaced at CHPP-1.
* Major repairs were made to the power equipment.
Construction of ash dumps
To ensure the smooth operation of the plant, the following works were performed:
* Reconstruction of combined ash and slag removal system at CHPP-2.
* Reconstruction and expansion of the ash dump of CHPP-3.
Main environmental measures
As part of the fulfillment of Investment Obligations, the burner devices of the CHPP-2 and CHPP-3 boilers were upgraded.
Implementation of the measures implemented in 2013 allowed:
• Increase the utilization rate of the installed electric capacity of AlES JSC by 0.5% compared to the planned value and amounted to 48.2 % due to an increase in electricity generation by 50,021 thousand kWh.
* Reduce the adverse environmental impact of nitrogen oxides from JSC AlES ‘ energy sources at CHPP-2 and CHPP-3 boilers by 440 tons / year.
* Reduce the number of technological failures in AlES JSC as a whole from 171 to 148 (13%).

______________________________________________________________________________________

Almaty Electric Power Stations JSC is a part of Samruk-Energo JSC. Almaty electric power stations are the main energy source of the Almaty region and provide about 70% of the heat of the district heating zone and 72% of electricity.
The power complex of JSC “AlES” includes:: CHPP-1, CHPP-2, CHPP-3, Western thermal complex, Kapshagai HPP, Cascade of Almaty HPPs, Production and repair Enterprise “Energoremont”, CPVT.

INVESTING IN A BUSINESS

At regular public hearings, the management of JSC “Almaty power plants” spoke about the fulfillment of the company’s investment obligations for 2013
It should be recalled that JSC “Almaty power plants” (Ales) is an energy – producing organization for the production of electric and thermal energy in Almaty and the adjacent region. The energy sources that are part of the company were built in Soviet times, are morally outdated and need to be modernized and reconstructed for further operation.
According to the chairman of the Board of JSC” ales ” Nurlan Mukhamed-Rakhimov, most of the funds allocated for the implementation of investment obligations are aimed at increasing the volume and maintaining the level of production. As well as the construction of ash dumps, conservation activities and reduction of production costs.
Part of the planned repairs were carried out ahead of schedule, which allowed the company to increase capacity and reduce accidents by 1.5 times from 2010 to 2013.
Currently, according to the chairman of the management board, the cleaning of the channel in the lower section of the Kapshagai hydroelectric power station continues. The subsequent implementation of this work will increase the power generation capacity by 2.5 MW.
The replacement of physically and morally outdated equipment in the hydroelectric power station Cascade leads to an increase in electricity and an increase in energy production.
The construction of water intakes at CHPP-1,2 continues. These measures are necessary to reduce water costs used in boilers. The implementation of the set goals amounted to 72.2 million tenge per year. it entails saving funds for the purchase of water in the amount of tenge.
The modernization of fixed assets to maintain the current level of production also includes the transfer of the roller mill to CHPP-1. The construction of ash dumps at CHPP 2,3 continues.
The company’s management pays special attention to environmental issues. For this purpose, the modernization of combustion devices of boiler units is being carried out at CHPP 2,3. The implementation of these measures will reduce the number of nitrous oxide emissions into the atmosphere to 7.2 thousand tons per year.
Since energy sources belong to the most important state facilities, work is underway to increase their technical strengthening and equipment with security and alarm systems.
According to Nurlan Mukhamed-Rakhimov, the impact of the work carried out today has made it possible to increase electricity generation by 50 thousand kWh. The adverse impact of energy sources on the environment and, in general, the number of technological violations has decreased.
At the end of the speech, the chairman of the management board gave detailed answers to the questions asked.

Irina TULINOVA

UNDERSTANDING THE BALANCE OF INTERESTS

The Almaty Electric Power Plants company reported to the public.
In the competition of the growth rate of energy production costs and tariffs for consumers, the undisputed victory is for expenses. So, if the total prices of the tariff components grow by 7-8% per year, then the growth rate of the tariff itself for consumers is 4-5%. That is, the growth rate of costs is higher than the growth of tariffs. The difference grows with a cumulative effect, which, unfortunately, leads to a decrease in the investment part. If the growth rates of costs and tariffs were the same, then the volume of investment growth in the energy complex would remain and even increase every year.
Such figures and arguments were announced at the public hearings on the annual report on the fulfillment of investment obligations of JSC AlES over the past year. The traditional meeting of the company’s top management and the public with the participation of representatives of government agencies and the media was held in the conference hall of CHP-1 and also traditionally focused on key energy issues: production efficiency, tariff level, return on investment, ecology. The interests of consumers – one might say with a public bias – were now represented by AREM expert, personal pensioner and public figure Sholpan Aitekova.
Answering questions from members of the public, the energy industry presented and commented on the indicators of the past year in sufficient detail. In particular, as the Chairman of the Board of Almaty Electric Power Plants JSC Nurlan Mukhamed-Rakhimov noted, electricity production in 2013 increased from 5.18 billion kW.A year earlier, to 5.23 billion kWh, the volume of electricity sales also increased from 4.44 billion kWh.up to 4.51 billion kWh. At the same time, the average annual electricity tariff remained unchanged at 7.8 tenge/kWh. As the head of AlES noted, the work aimed at increasing production volumes was completed by 100.8%. The over-fulfillment is due to the fact that part of the work planned for the current year was completed ahead of schedule. All planned environmental measures have been fully implemented. A few energy companies fell short of the plan for the implementation of investment measures aimed at reducing production costs and maintaining production levels, which was due to external factors – long delivery times of equipment and approval of the project in the RSE “Gosexpertiza”.
And thanks to the tender, we managed to save money on the construction of ash dumps.
I must say that economy, efficiency and ecology have become the key benchmarks of the Almaty energy complex in the performance of production tasks over the past year. The company conducted a large-scale modernization and reconstruction of production facilities, which allowed to reduce the level of depreciation of fixed assets, as well as implement a large energy saving program and reduce its own needs. From the point of view of consumers, this is important. Firstly, due to the fact that the reliability and fault tolerance of the system increases. Secondly, the mobilization of domestic resources provides savings, which partially compensates for the gap between selling tariffs and the increase in production costs. For example, only the implementation of the project for the construction of its own water intake of CHP-1 and CHP-2 will eventually save up to 72 million tenge this year. Another example: after clearing the channel bed, the Kapshagai HPP will be able to generate additional electricity for an average of 16 million tons.kWh per year.
But on the other hand, some projects, for example, the transition from cheap coal to more environmentally friendly gas significantly increases the company’s costs. According to the company, coal, even taking into account the high delivery price, which is higher than its cost, turns out to be almost twice as cheap as gas. Production workers are in a vice between the economy and the environment. And if the legislative restriction on tariff growth does not allow to compensate for this gap, then cost optimization for the item “own needs” has now become one of the directions for reducing costs and increasing production and sales volumes. This issue was also discussed during the public hearings. Many people remember that in the early 90s, when power engineers did not have the means to develop production, this eventually led to a crisis in the energy system, interruptions in energy supplies, and rolling blackouts. Today, the public, the energy industry, and the regulator advocate a reasonable balance of interests, in which the energy sector will be able to develop and modernize, and consumers will not massively switch to the category of defaulters due to the unaffordable tariffs. The achievement of the main and permanent goal of JSC AlES: “Light and heat – in every home” should not be achieved “at any, even fatal cost.” And, as the discussion showed, the public “does not thirst for blood.” But he craves an understanding of the item-by-item, detailed expenses. That’s what Mr. Mukhamed-Rakhimov ran to provide for the future. That was the end of it.

Alevtina DONSKIKH, Almaty

REPORT ON THE IMPLEMENTATION OF THE INVESTMENT PROGRAM OF JSC ALES FOR 2013, TAKING INTO ACCOUNT CLARIFICATIONS AND CHANGES IN THE PRODUCTION OF THERMAL ENERGY

Otchet invest programmy 2013

 

2Otchet invest programmy 2013jpg

JOINT-STOCK COMPANY “ALMATY ELECTRIC STATIONS” NOTIFIES CONSUMERS AND OTHER INTERESTED PARTIES ABOUT HOLDING A HEARING ON THE ANNUAL REPORT OF THE ACTIVITIES OF JSC ALES FOR 2013: #10

“Almaty power plants “JSC informs that on May 06, 2014 at 10.00 at the address: Almaty, Algabas microdistrict, street No. 7, house 130 (Assembly Hall of CHPP-2) public hearings will be held to discuss the action plans for Environmental Protection developed for the Departments of” “Western thermal complex “”ales “” JSC (WPC), fuel intake and unloading Center (TSPVT), CHPP-1 and CHPP-2. the production sites of the departments are located in Auezov, Zhetysu, Almaty and located in Alatau districts.
We invite the interested public, public and non-governmental organizations and associations, mass media to participate in public hearings. If you have any questions, please call 8(727)238-16-61.

PUBLIC HEARINGS. 06 MAY 2014

JSC ” ales “informs: on May 06, 2014 at 10:00 am, a public hearing will be held at the address: Almaty, Algabas microdistrict, street No. 7, house 130 (meeting room of CHPP 2) to discuss environmental protection plans for the Departments of CHPP 1 and CHPP 2 (CHPP-2) of JSC” ales”. The production site of these departments is located in the Auezovsky, Zhetysu and Alatau districts of Almaty.
We invite all interested parties, Public Associations and non – governmental organizations and institutions, mass media to take part in the public hearing. If you have any questions, please call 8 (727) 238-16-61.

THOSE WHO WORKED DO NOT SHY AWAY FROM REPORTING

An urgent problem is the provision of heat and hot water to such a large metropolis as Almaty. Therefore, companies operating in this area are recognized as monopolists, whose activities cause constant discussions on the part of the townspeople. For example, one of the largest companies in the city, which is a subject of natural monopolies for the production of thermal energy, is JSC “Almaty power plants”. The company is included in the State Register of natural monopoly entities due to the fact that it produces thermal energy for the city of Almaty and the Almaty region and supplies water through main pipelines (prepares chemically treated water). In accordance with subparagraph 7-3 of paragraph 7, Article 7 of the law of the Republic of Kazakhstan” on natural monopolies and regulated markets”, annual public hearings of JSC” Ales ” have become a tradition.
On March 26, 2014, in the conference hall of CHPP – 1 of JSC” Ales”, a hearing was held before consumers and other interested parties on the report on the implementation of tariff estimates for the services of heat generation and water supply by main pipelines (preparation of chemically treated water) in 2013. The hearing was attended by director of the Department of the agency for regulation of natural monopolies in Almaty Dauren Zhandarbek, representatives of JSC “Samruk-Energo”, as well as independent experts, consumers, media representatives. Chairman of the Board of JSC “Ales” N. T. Mukhamed-Rakhimov reported at the hearing.
Last year, Almaty power plants JSC carried out a lot of work aimed at improving the efficiency of the power complex. In connection with this, we can name the completion of the construction of the boiler house, the introduction of a highway connecting CHPP 2 and CHPP 1. In his report, the chairman of the Board of JSC “Ales” N. T. Mukhamed-Rakhimov drew the audience’s attention to the activities of the company aimed at implementing the investment program.
In total, in 2013, the amount of funds disbursed in the implementation of investment measures by Ales JSC amounted to 9.2 billion US dollars.tenge. In particular, 877.4 million tenge was allocated for the construction of boiler houses, including collector water distribution and tank batteries.the tenge was spent. In order to reduce emissions of nitrous oxide, the restructuring of the combustion devices of boiler units at CHPP-1 amounted to 292.4 million tons. the work of the tenge has been done.

Speaking about the main financial and economic indicators of the activities of ales JSC in 2013, N. T. Mukhamed – Rakhimov noted that the company suffered losses in the amount of 815 million tenge in the production of thermal energy, and in the supply of water by main pipelines (chemically treated water) in the amount of 723.6 million tenge. According to the head, the main reason for the increase in costs for the production of thermal energy and the preparation of chemically treated water was the increase in fuel prices and prices for its transportation.
In addition, the report noted a decrease in the volume of heat energy consumption of heating networks by 14 percent, and the consumption of chemically treated water by 25 percent.
JSC “ales” has formed an investment program for 2014-2016.
In accordance with the long-term development strategy of ales JSC, the annual amount of modernization, reconstruction and maintenance of the current state of production in 2014-2022 amounted to млрд 111.4 billion. capital investments in tenge are planned.
Within the framework of the implementation of the investment program for the production of thermal energy – 13.1 billion rubles.”I don’t know,” he said.
Regulated service tariffs cannot compensate for the required amount of investment investments in full.
In this regard, during the analysis of the financial and economic results of the activities of ales JSC, it was found that the cost part of tariffs for regulated services is steadily increasing. The increase in the cost of generating heat energy and preparing chemically treated water was facilitated by an increase in prices for services provided by other organizations providing fuel and transporting it.
“However, the report showed that” “Almaty power plants “” JSC worked quite intensively over the past year.” Moreover, now there will be a time when they say that “those who work do not shy away from reporting to the public.”

Kuttybek AIMAKHAN

LONG-TERM STRATEGY OF ALES AT CHP-1, REGULAR PUBLIC HEARINGS WERE HELD ON THE PROVISION OF REGULATED SERVICES TO ALMATY ELECTRIC POWER PLANTS JSC

tec1 smi

The Chairman of the Board of JSC AlES delivered a report on the activities of JSC Almaty Electric Power Plants (AlES) to the audience
Nurlan Mukhamed-Rakhimov.
According to him, in 2013 the company fulfilled investment obligations for 9.2 billion tenge, including 1.6 billion for equipment for the production of thermal energy. The funds were spent on the modernization of burner devices, reconstruction of the water treatment plant, power supply to the central thermal distribution point of the boiler house, gas control point, etc.
The overhaul of the equipment for the production of thermal energy for 1.3 billion tenge was carried out.
Speaking about the main financial and economic indicators of the activity of JSC AlES in 2013, Nurlan Mukhamed-Rakhimov noted that the company suffered losses from the production of thermal energy by 815 million tenge and when supplying water through main pipelines (chemically treated water – 723.6 million tenge). The main reasons for the increase in costs, and actually losses, for the production of thermal energy and the preparation of chemically treated water, according to the head, were the increase in the cost of fuel and its transportation, as well as water supply services.
The report also mentioned a decrease in the consumption of thermal energy by 14 percent and chemically treated water by 25 percent by the heating networks of Almaty.
Work is also continuing with consumers of AlES JSC’s services to repay accounts receivable.
At the end of his speech, Nurlan Mukhamed-Rakhimov spoke about the prospects of the company’s activities. In particular, according to the long-term development strategy of JSC AlES for 2014-2022, capital investments are planned for renovation, reconstruction, modernization and maintenance of the current production level totaling 111.4 billion tenge. As part of the implementation of the investment program for the production of thermal energy  13.1 billion tenge.
It was also noted that tariffs for regulated services do not fully cover the required amount of investment. In this regard, due to a shortage of own funds, it is planned to attract borrowed money and finances from the republican budget for the timely implementation of priority projects in order to reliably, uninterrupted supply of consumers with thermal energy.
At the end of the event, the head of JSC AlES gave comprehensive answers to all the questions that arose during the meeting.

Irina TULINOVA

THE NPP ENERGY COMPLEX WILL CONTINUE MODERNIZATION

In 2013, investments in the development of JSC “Ales” amounted to 9.2 billion rubles. “no,” he said.
During the public hearing of these data, Chairman of the Board of JSC “Almaty power plants” Nurlan Mukhamed-Rakhimov reported and made a report on the results of the work of Ales in 2013. Traditionally, the company’s reports arouse the interest of the public. Along with representatives of authorized and state bodies, representatives of consumers, Public Associations, the media, independent experts came to the meeting with Power Engineers. Such public reports contribute to a better understanding by the public of the situation in the energy complex, the tasks it solves and the validity of the tariff policy. During the year, ales repeatedly told and showed the press about the modernized or new facilities of the energy complex. Now the main indicators and numbers are named.
In particular, 1.6 billion of the above amount. more than tenge was allocated only for the modernization of heat energy production. Reconstruction was carried out at a number of facilities, new equipment was purchased and installed, and construction work was carried out.
Nurlan Mukhamed-Rakhimov also announced the creation of an investment program for 2014-2016. According to it, 13.1 billion rubles are allocated for the production of thermal energy alone. it is planned to invest in tenge. In general, in accordance with the long-term development strategy of ales JSC for 2014-2022, capital investments to update, reconstruct, modernize and maintain the current level of production amounted to млрд 111.4 billion.it is estimated in tenge.
The number of development costs is very high. Therefore, it is expected that the main financial and economic indicators of Ales for regulated services in 2013 in the framework of capital-intensive modernization went to minus. Thus, the losses from the production of thermal energy amounted to 815 million rubles. the annual revenue amounted to KZT 12,564 million.the damage amounted to KZT 13,379 million. “no,” he said. At the same time, 4.953 million. Gcal heat energy was sold, a decrease in consumption compared to 2012 by 10% -. made up. Losses on the service “water supply through main pipelines”amounted to 723.6 million. “no,” he said.
-Analysis of the results of financial and economic activities for Regulated Services shows that the cost – effective part of the tariff is constantly growing,-Nurlan Mukhamed-Rakhimov noted. – The main reasons for the increase in costs for the production of thermal energy and water preparation are the increase in the cost of fuel and its transportation, water supply services, materials and services of third-party organizations. And tariffs for regulated services do not cover the required amount of investment investments in full.
To solve all existing problems and due to a shortage of its own funds, the company intends to attract borrowed funds and funds from the Republican budget. This will allow timely implementation of priority projects for reliable, uninterrupted supply of heat energy to consumers in the future.

Alla DEMENTYEVA, Almaty