The Cascade hydroelectric power station: the first project of GOELRO in the Verensk region
Back
05.02.2026

The Cascade hydroelectric power station: the first project of GOELRO in the Verensk region

One of the main sections of the GOELRO plan of 29 November 1920 was devoted to the task of electrifying the Turkestan region. The document included Semirechye, comprising the present-day Almaty region, and in particular the mountainous area surrounding the city of Vernyi, where, years later, as planned, a unique cascade of hydroelectric power stations was built.

“For Turkestan, the issue of cheap energy is of the utmost importance. Cheap water and cheap energy, supplied to those places where people need them, constitute the main factors in the development of Turkestan. The natural conditions of Turkestan are highly favorable: it abounds in hydropower, which is easy and cheap to utilize. From the mountain ranges bordering the valleys of the heartland of Turkestan and Semirechye, watercourses burst forth, cutting through narrow fissures in the limestone and conglomerate mountain folds. By damming these narrow gorges with artificially constructed dams, the water level of these rivers can be raised by several dozen fathoms, creating favorable conditions for the utilization of hydraulic energy”.

GOELRO Plan, 1920

The plan to build hydroelectric power stations on the Mountain Rivers in the foothills of Vernyi (Almaty) in the 1920s was already on the table of development projects for the Soviet state. However, the project was classified as a second-phase undertaking. The document included between 20 and 30 water turbines with generators ranging in capacity from 2,000 to 10,000 kW. Overall, the cost of constructing the second-phase stations was estimated at 30-51 million rubles. When the plan was drawn up, the priority and feasibility of building power stations on rivers, including those near Vernyi, were justified by the construction of the Pishpek – Vernyi railway. But it did not work out.

In February 1939, Maxim Saburov, Deputy Chairman of the USSR State Planning Committee, reiterated the need to build hydroelectric power stations on the mountain rivers near Almaty. He considered it necessary to develop the project and consider dividing the stations into several smaller hydroelectric power stations. A few years later, amidst the harshest conditions of the Great Patriotic War, this is precisely what was done.

In 1942, the design and preparatory work for the hydroelectric power station cascade were commenced by the Leningrad branch of the ‘Gidroproekt’ Institute, and construction of the first power stations began in April 1943. The preliminary design envisaged the construction of 11 hydroelectric power stations utilizing a 1,500-metre head of the river. Small power stations were designed first, as they were easier to build: HPP No. 11 with a head of 32 m and HPP No.5 with a head of 92 m.

Simultaneously with the start of construction of the Cascade HPPs, on 9 August 1943, by Order No.157 of the People’s Commissar for Power Stations of the USSR, the Kazakh Regional Energy Administration ‘Kazakhenergo’ was established in Almaty, with the Almaty Central Power Stations, the Power Grid Administration and the hydroelectric power stations under construction once they became operational.

Construction of new hydroelectric power stations began in 1943, using the method of mass mobilization. By April 1944, Hydroelectric Power Station No. 11, with a capacity of 0.8 MW, had come into operation, and in September of the same year, similar power stations Nos. 5, 9 and 10 began generating electricity. The turbines for most of them were manufactured in Almaty.