First Heat from the New CHPP-2: From Boiler Ignition to Supplying Energy to the Grid
Back
03.11.2026

First Heat from the New CHPP-2: From Boiler Ignition to Supplying Energy to the Grid

Commissioning work continues at the construction site of the new A.Zhakutov gas-fired CHPP-2 plant. A major milestone was the first delivery of thermal energy from the hot-water boilers to the municipal heating network. This marks a significant stage in preparing the new equipment for commercial operation.

Before heat could be supplied to the network, specialists had to carry out a comprehensive series of inspections and tests. Hot commissioning is a process in which equipment is started up, the load is gradually increased, and performance is tested under conditions closely simulating actual operation.

It all begins with verifying the readiness of the boilers, pumps, pipelines, gas supply systems, and automation. Particular attention is paid to the functionality of safety systems, equipment leak-tightness, and water circulation. Only after confirming that all systems are ready do specialists proceed with igniting the burners.

Next comes the gradual warming up of the boilers. Commissioning engineers monitor water temperature and pressure, combustion stability, and the performance of auxiliary equipment. As the required parameters are reached, the thermal load is increased to test boiler operation across various modes.

The next crucial step is delivering heat to the network. Water heated in the boilers begins flowing into the district heating system. Throughout this process, specialists continuously monitor the temperature, pressure, and flow rate of the heat transfer fluid, gradually increasing the load in accordance with the testing program.

Commissioning does not end there. Up next are further testing of the equipment under load, tuning of the automatic control systems, testing of process safety systems, and determining the optimal operating modes.

Behind every such launch is the coordinated teamwork of engineers, commissioning technicians, operations personnel, and contractors. No detail is minor here: the reliability of the entire system depends on the proper calibration of every single unit.

Delivering the first heat to the grid is a major milestone in the construction of the new gas-fired CHPP-2. Much work still lies ahead, but the equipment is already being proven not just through isolated tests, but through the actual generation of thermal energy.

For Almaty, this is another step toward creating a modern and more environmentally friendly district heating system for the city.