Precision at Every Stage
Back
09.09.2026

Precision at Every Stage

A scheduled major overhaul of hydropower unit №3 is underway at the Sh.Chokin Kapshagai HPP. The work began on August 18 and will continue until December 15, 2026. To date, 25 percent of the planned scope has been completed. The repairs are being carried out by a contractor.

Before disassembly, specialists conducted vibration tests on the hydropower unit. These tests allow them to record its performance parameters before the overhaul and compare the readings after all work is completed.

The unit is currently being disassembled. The generator spider and rotor have already been dismantled, and large components have been moved to the assembly area.

It is after the dismantling that the extensive and meticulous work begins: inspecting the equipment, taking measurements, identifying defects, and determining the scope of restoration.

“It’s important not to rush here. Each component must be carefully inspected and its condition assessed before a decision on further repairs is made,” notes Alibek Tastanbekov, the plant director.

Work is proceeding simultaneously on several fronts. The generator and turbine bearings and the thrust bearing are being repaired, and the oil receiver is being disassembled. Specialists are working in the runner chamber, replacing the shaft seal.

Particular attention is paid to the bearing assemblies and the thrust bearing. During operation, they bear significant loads, so the precision of measurements and adherence to repair procedures are crucial here.

“Everything in a hydropower unit is interconnected. The quality of the repair of each component ultimately affects the performance of the equipment as a whole,” explains Alexander Miroshnichenko, head of the plant’s electrical machinery workshop.

In parallel, the air coolers are being repaired at the contractor’s facility.

Ahead lies further repair work, equipment assembly, adjustment, and testing. Upon completion of all scheduled work, hydropower unit №3 will undergo the necessary inspections and be prepared for continued operation.

At the plant, the overhaul is proceeding on schedule. For the power engineers, this is routine yet critical work, where the final result truly depends on precision at every stage.