WTC: The ‘thermal heart’ of Almaty
Initially, there was no single project for the Western Thermal Complex (WTC). It all began with the construction of the Western District Boiler House, which was intended to serve the needs of the Almaty Cotton Mill and formed part of the Directorate of Light Industry Enterprises Under Construction. The boiler house was commissioned in 1963.
From the mid – 1960s, the city grew before our very eyes. Zhumagali Ormambekov remembers this dynamic; as a young man in 1968, he took a job as a fitter maintaining heating networks at the Heating Networks Directorate of the ‘Alma-Ata energo’ Regional Energy Administration.
“In those parts of the city where the ‘Aksai’ and ‘Orbita’ neighbourhoods are now, there used to be fields where they grew maize, then cucumbers and tomatoes. It was state farm land. We worked there as students and always said we were going to ‘jaylau’,” recalls Zhumagali Satyganovich, who later, in 2000, became head of WTC.
Although the boiler house in those years was under the administrative control of the AHBC, it supplied heat and steam to both the plant and the western districts of Almaty. The ZRK supplied heat to the factory: there was a process here involving the steam treatment of threads, and it heated the homes in the new neighborhoods №1 and №2. ZRK’s steam boilers supplied steam to industrial enterprises located in the area: in addition to the AHBK, these included the City Foodstuffs Plant, the Fittings Factory and other small organizations, of which there were many at the time.
From the late 1960s and throughout the 1970s, the development of Almaty’s heat supply moved towards the construction of powerful district heating plants, which made it possible to close 735 small boiler houses in Almaty by 1981. At the same time, the South-Western District Heating Plant (SWDTP) was built.

The pace of development in the capital of Kazakhstan dictated the need to increase heat output and distribute it throughout the city during the 1970s and 1980s. High demand and the existing infrastructure predetermined the further evolution of the ‘factory boiler house’ into a fully-fledged urban heating complex. A more powerful heating hub began to take shape around the ZRK.
In 1980, alongside the construction of CHPP-2, a pipeline was laid from this station to the ZRK. This ensured the reliability of the city’s heat supply. The Central Heat Distribution Point (CHDP) was commissioned; it is currently connected to seven heat mains and Pumping Station №6 with storage tanks, supplying the city with heat and hot water.
Today, the CHPD handles two-thirds of the water circulating in the city’s heating networks and is, in essence, the ‘thermal heart’ of Almaty.