HPP: The Struggle for Light, Ecology, and… Bread

As was customary in the USSR – a country of rigid planning and powerful bureaucracy – discussions about the HPP construction project in Alma-Ata began long before construction started, back in 1954. At that time, the Council of Ministers of the Kazakh SSR resolved to select sites for the construction of a power plant with a capacity of 50-100 thousand kW within the “Kazakhenergo” system. The development of technical documentation and all related issues, including environmental ones, began immediately.

In 1956, a Decree of the Council of Ministers of the USSR designated the territory and commencement of construction for the GRES near the capital of Kazakhstan, beyond the village of Pokrovka. The station, like all construction projects of that era, began with tents in an open field, surrounded by ravines and wasteland. According to a report by State Sanitary Inspector Krynsky and HPP Chief Engineer Merzlyakov, “part of the builders’ families is housed in seven tents. The tents are single-walled, some of which have holes. The tents do not have wooden floors. The tent city does not have a lavatory.”

This state of affairs satisfied neither the workers nor the state sanitary and epidemiological services of the Iliysky District and the region. Consequently, official reports were drawn up and detailed directives were issued. These included: “immediately, and no later than July 29, 1958, cease the operation of the shower facility, which is supplied with water from the Malaya Almatinka River… The operation of the camp is possible only on the condition that double-walled, insulated tents with Plexiglas windows and wooden floors are provided…”

It was also ordered to: “install the temporary canteen’s trash container on a concrete platform, and replace the concrete plant’s cesspit with a non-absorbent one.” The “discharge of treated domestic and fecal wastewater from the Alma-Ata HPP into the Malaya Almatinka River” was prohibited. An agreement was reached for the … “discharge of wastewater after full biological treatment into the HPP ash dump, where the wastewater shall circulate in a closed hydro-ash removal system”.

Many workers were dissatisfied with the living conditions; some couldn’t endure them and left. And some… began to build their own temporary shelters without any formalities or documents.

One such curious incident has been preserved in the history of the GRES. A worker by the name of Fedyukov, who, like everyone else, initially lived in a tent, built a small adobe house next to a well. The Sanitary and Epidemiological Service (SES) ordered it to be demolished, as it violated sanitation standards. The demolition order for the temporary shelter was signed by Director Kobyzev, who instructed that this worker be placed on the housing waitlist.

The director himself spent a long time trying to persuade the unauthorized builder, pointing out that he “should obtain a land plot from the HPP Construction and Installation Directorate (SMU) and move the construction of his house there. The HPP SMU will provide the necessary assistance with building materials at your own expense for the construction of the house on the allotted plot.”

But Comrade Fedyukov refused to accept the directive. Nevertheless, the builder’s housing issue was subsequently resolved legally, in accordance with the waitlist.

One can understand Comrade Fedyukov. As one can understand the SES and the HPP director. But what is important is that, aware of the builders’ difficulties, the construction of a new settlement had begun long before the plant was commissioned. This started with the erection of three-story buildings on Titov Street and two-story timber-frame-and-reed houses with cement cladding on Abay Street. The Council of National Economy, anticipating the plant’s launch, provided for the construction and commissioning of a 100-child kindergarten costing 500 thousand rubles and a 100-child nursery for 500 thousand rubles in 1958.

1.7 million rubles were allocated for the construction of a school, which was planned to be commissioned in 1959. All these facilities, as well as the settlement, were built – it is now known as the HPP settlement, and today as “Energeticheskyi.”

Another touch on the director’s portrait and the order of the time. A unique fact about the rules that existed then was documented on August 11, 1958: “In connection with my departure for grain harvesting work on the assignment of the Central Committee of the Communist Party of Kazakhstan – I hereby order: for the period of my departure, the duties of the director of the Alma-Ata HPP under construction shall be temporarily assigned to the head of the directorate’s production department, Comrade Alexander Mikhailovich Stamm. Director of the power plant under construction, A.Kobyzev.”

Construction is construction, but a party order is a party order, and so Comrade Kobyzev went off to the grain harvest… This, however, did not prevent him from continuing to manage the construction and later heading the station, whose first power unit was commissioned and generated its first kilowatts of electricity on March 30, 1962.