The A.Zhakutov CHPP-2 Maintenance Campaign: Reliability is forged in summer
Back
26.06.2026

The A.Zhakutov CHPP-2 Maintenance Campaign: Reliability is forged in summer

The 2026 maintenance campaign at the A.Zhakutov CHP-2 continues. These scheduled works are a critical part of preparing the plant for the 2026-2027 autumn-winter period and are aimed at ensuring a reliable supply of heat and electricity to consumers in Almaty and the Almaty region.

For power engineers, the summer period is a time of large-scale and critical work. While the city goes about its daily life, employees of CHPP-2 and the “Energoremont” Production and Maintenance Enterprise are conducting major overhauls and routine repairs on the main and auxiliary equipment. Their primary task is to prepare the plant for stable operation under maximum winter loads.

One of the key projects in this maintenance campaign is boiler unit №4. It is undergoing a major overhaul, which includes replacing the rear waterwall, the second-stage air preheater cubes, and the gas ducts. In parallel, routine maintenance is being performed on turbine unit №5: specialists are conducting diagnostics, inspections, and restoring necessary components, as well as replacing worn-out parts and checking mechanisms.

Every profession is essential to this effort. Fitters dismantle and install equipment, perform defectoscopy, and repair and adjust mechanisms. Samat Sultanov, a fitter at the main boiler equipment repair section of the “Energoremont” Production and Maintenance Enterprise, notes:

– There are no minor details in maintenance. Every operation must be performed with precision and quality. We understand that we are preparing the equipment to operate during peak load periods, so we carefully inspect every component.

Welders also bear a special responsibility. They are involved in replacing elements of the boiler unit, performing welding, and restoring metal structures. As Talgat Akhaev, a welder at the turbine equipment repair section of the “Energoremont” Production and Maintenance Enterprise, says:

– Our work requires precision, experience, and strict adherence to technical procedures. The reliability of the equipment depends on the quality of each welded joint, so all work is performed with special attention and mandatory quality control.

The employees of “Energoremont” and its contracting organizations work as a single team. Their daily work demands high qualifications, discipline, compliance with industrial safety requirements, and mutual support.

Yermek Baygaraev, Deputy Chief Engineer for Maintenance at CHPP-2, emphasizes:

The maintenance campaign is proceeding according to schedule. We are monitoring the deadlines, scope, and quality of work at every stage. Our main goal is to ensure the reliable and trouble-free operation of the equipment during the 2026-2027 heating season.

These measures will enhance the operational reliability of the equipment and ensure a stable supply of heat and electricity to consumers during the winter period.

The A.Zhakutov CHPP-2 is preparing for winter today to ensure that the homes of Almaty residents have light and warmth.