Results of implementation of the approved development plan of Almaty Electric Power Stations JSC for 2017

Results of implementation of the approved development plan of Almaty Electric Power Stations JSC for 2017

Results of the implementation of the approved development plan of Almaty Electric Power Plants JSC for 2017

In accordance with the approved development plan, AlES JSC carried out measures to replace, upgrade, reconstruct, re-equip existing assets, new construction, as well as maintain the current production level in the amount of 5,645,523 million tenge (including 3,908,495 million tenge according to the cap plan. construction).

As part of the execution of the approved development plan, AlES JSC developed projects with further implementation and carried out the following main activities:

– Reconstruction and expansion of CHP-1 with conversion to gas and installation of CCGT/GTU. Development of the PSD;

– Development of design and estimate documentation for the reconstruction of the central checkpoint of CHP-1 and entrance gates in the amount of 3 pieces;

– Reconstruction of the combined ash and slag removal system of CHP-2 (stage 5). Development of the PSD;

– Reconstruction and expansion of the ash dump of CHP-3. Turn 2. Development of the PSD/

– Reconstruction of the combined ash and slag removal system of CHP-2 (Stage 5)

Execution of the CMP

До реконструкции                                                      в процессе реконструкции

2018-11-14 162023

The planned completion of the work is the 2nd quarter of 2019 (according to the schedule for the implementation of the CMP for 2017-2019).

– Reconstruction and expansion of the ash dump of CHP-3. Turn 2. Execution of the CMP

Before the reconstruction                                                   in the process of reconstruction

2018-11-14 162033

The planned completion of the work is the 1st quarter of 2018 (according to the schedule for the implementation of the CMP for 2017-2018).

– Reconstruction of the ORU equipment-35/100/220 kV. Kapchagai hydroelectric power station. Execution of the CMP.

Before and after reconstruction

2018-11-14 162042

– Installation of an automatic barrier with a control panel for access to the territory of Kapshagayskaya HPP. Performing the QMS.

2018-11-14 162112

Reconstruction with replacement of the charging and recharging device for VB VARTA type batteries. Kapchagai hydroelectric power station.

Before replacement  after replacement

2018-11-14 162131

– Comprehensive turnkey construction works. Gasification of heating and hot water supply of HPP Cascade facilities

Before and after reconstruction

2018-11-14 162151