During his official visit to Almaty, Nurlybek Nalibayev toured CHPP-2 and CHPP-3
Back
18.05.2026

During his official visit to Almaty, Nurlybek Nalibayev toured CHPP-2 and CHPP-3

During his official visit to Almaty, Nurlybek Nalibayev toured CHPP-2 and CHPP-3, where he inspected the progress of the large-scale modernisation works.

CHPP-2, located in the Alatau district of Almaty, is the city’s largest source of heat. The main objective of the modernization project is to ensure a stable supply of heat and electricity by converting the energy complex to natural gas, as well as to reduce harmful emissions into the atmosphere. The project involves the commissioning of a modern gas-fired power station with a thermal capacity of 952 Gcal/h and an electrical capacity of 600 MW.

Three gas turbines and generators have been installed as part of the project. Equipment delivery is 99% complete. Construction of ancillary infrastructure and roads has been completed. The overall progress of construction and installation works at the main sites stands at around 55%. Work is currently continuing on the main building, the hot-water boilers, the water and gas treatment facilities, and the electrical infrastructure. All works, including the delivery of the main equipment, are proceeding in accordance with the approved schedule. The project is scheduled for completion by the end of 2026.

In addition, the First Deputy Prime Minister inspected CHPP-3, located in the Ili District of the Almaty Region. As part of the reconstruction, a combined cycle power plant with a capacity of at least 450 MW will be built at the station, and worn-out equipment will be replaced. The contractor is a consortium of Kazakhstani companies.

Work is currently underway on the pile field; the first set of the gas turbine unit has already been placed on the foundation, and some of the equipment has been installed on the construction site. The design and estimate documentation is currently undergoing state expert review. Completion of the refurbishment is scheduled for 2027.

Nurlybek Nalibayev emphasized that issues concerning the development of Almaty and improving the quality of life for the city’s population are under the special supervision of the Head of State. The Government has taken all necessary measures to ensure the reliable and efficient operation of energy facilities. In this regard, he instructed that the modernization works be completed on time, without falling behind the established schedule.