Chairman of the Management Board of Samruk-Energy JSC Reviews Progress on CHPP-2 Modernization and CHPP-3 Reconstruction
Ansar Aidarov, Chairman of the Management Board of Samruk-Energy JSC, visited the construction sites of Almaty CHPP-2 and CHPP-3 as part of a working visit. During the visit, he reviewed the progress of strategic energy projects and held operational meetings with representatives of the project owner and general contractors.

At Almaty CHPP-2, the project has entered an active phase of commissioning activities. Since October 31, 2026, the new hot-water boiler plant has been supplying thermal energy to the district heating network.

Hot commissioning activities are currently underway, with preparations in progress for the phased commissioning of three gas turbines and one steam turbine. Today, November 25, the third gas turbine manufactured by Siemens Energy was successfully fired up. The first supply of electricity to the grid is scheduled for November 30, 2026.

At Almaty CHPP-3, the Chairman of the Management Board of Samruk-Energy inspected the progress of construction and installation works under the station reconstruction project, which involves the installation of combined-cycle power units with a total capacity of up to 544 MW. He also reviewed the current status of the construction site.
To date, 95% of the main technological equipment has been delivered to the site. Installation of the main and auxiliary equipment for Gas Turbine Unit No.1, supplied by Ansaldo Energia, is ongoing, with progress reaching 69%. Installation of the first heat recovery steam generator is 90% complete. Preparatory works are underway to position the first steam turbine in its designated location, while installation of the steam turbine condenser has reached 50% completion. Works to enclose the thermal envelope of the main power building are 70% complete.

Following the visits to Almaty CHPP-2 and CHPP-3, instructions were issued to accelerate construction and installation works, strengthen oversight of contractors’ compliance with contractual obligations, and ensure that the new generating capacities are commissioned within the established deadlines.
The implementation of both projects remains under the close supervision of the management of Samruk-Energy JSC.