WTC: Heat begins its journey to the city
Back
08.10.2026

WTC: Heat begins its journey to the city

On October 5, one of the key stages of preparing the city for the heating season began in the heat supply area of the Western Thermal Complex: establishing circulation in transmission and distribution heating networks and connecting consumers.

Bringing the heating networks online is a complex technological process carried out in stages that requires coordinated teamwork between specialists from AlES JSC and Almaty Heating Networks LLP.

In the first stage, circulation is established in individual hydraulic zones. To achieve this, upon request from the AlES dispatch service, specialists open the bypasses between supply and return heating mains, bringing additional network pumps and necessary shut-off valves into operation. The network water temperature in supply mains is maintained at up to 70°C, and at around 65°C in the second, third, and fourth hydraulic zones.

On October 5, circulation was initiated in the second hydraulic zone within the WTC heat supply area, with one CHPP-1 network pump brought online.

As early as October 6, specialists began commissioning the first hydraulic zone. To ensure the required circulation, six CHPP-1 network pumps were brought into operation. Simultaneously, valves on the return pipelines of the heating mains and additional bypasses between supply and return lines were opened.

“Bringing the heating networks online is not an instantaneous process. Everything is carried out sequentially by hydraulic zones, with continuous monitoring of parameters. Our task is to ensure stable circulation, the required temperature regime, and the reliable operation of equipment as consumers are connected. During this period, well-coordinated staff actions and seamless cooperation with all involved services are particularly critical”, noted Yerzhan Abdyk, Director of the Western Thermal Complex.

As the network rollout progresses, consumers begin to be connected to the heating system. In accordance with a decree of the Almaty Akimat, heat is supplied first to social facilities – kindergartens, schools, and healthcare institutions. Residential buildings and other consumers are connected concurrently.

Particular attention during this period is paid to the quality of network water. From the moment circulation begins, specialists from the WTC chemical service conduct daily laboratory tests, checking, in particular, the levels of iron and suspended solids.

This monitoring continues until all consumers are fully connected and network water quality parameters stabilize.

For WTC specialists, bringing the heating networks online is an annual, well-practiced operation that carries great responsibility. The smooth progress of the heating season and the timely supply of heat to Almaty’s consumers depend on the precision of the utility workers’ actions and the coordinated efforts of all services.